ASE Systems
The Ergonomics and Productivity Specialists

Call us at
1-800-245-2163
for more information

Load Module System Case Studies

 

6-9-05

Todd-Ford Murphy Co., a mechanical contractor based in St. Louis Missouri, was hired by Toyota USA to install seven large Chiller units weighing 30-tons each in their new plant in San Antonio Texas; due to begin manufacturing operations in late 2006.

In his 20+ years as a project manager, Don Billington had observed on past projects other contractors using Fluid Film Technology to move extremely heavy loads with virtual ease and at a cost that undercuts other forms of load moving that he had looked into. As Don pursued his search for the correct mix of Air Caster equipment for his application he quickly concluded that ASE’s Load Module System would indeed allow his personnel to install the mammoth chillers on time and under budget.

Each of the 30-ton chiller units stood 13’ high x 9’ wide x 16’ long.

The “27-Heavy”, one of ASE’s most versatile rigging & machinery moving Air Caster systems, was chosen to move the 30-ton chillers. Rated at a total capacity of 96,000-lbs, the 27-Heavy #4K27NHDL can not only move loads “easily” at full capacity but also lite and delicate loads weighing just 5% of total capacity. The 27-Heavy’s versatility would allow Todd-Ford Murphy to enjoy a myriad of future load moving projects.

The Pictures!

Toy 1:
In the absence of a suitable dock facility due to the early stages of construction at the Toyota plant, Todd-Ford Murphy (TFM) constructed a temporary platform where the chillers could start their 150’ to 200’ trek to their final resting positions.

Toy 2:
The 27-Heavy’s load modules and interconnect hoses were laid out so that the load bearing surfaces of each chiller would set directly over the middle of each load module. In this application, the chiller’s load bearing frame was extremely narrow thus ½” thick metal plates were placed over the top of each load module to help distribute the load evenly over each module.

Toy 3:
As each of the chillers was delivered by the transportation company a local crane service would lift them from the Low-Boy trailers and place them on the adjacent platform with the Load Module System.

Toy 4:
Pull Cords were used to precisely position the “York” Chillers onto the load modules and also keep the workers at a safe distance.

Toy 5:
The Control Console and Interconnect Hoses were placed on top and draped over the chillers where ever possible; it is important to have the pathway free of any and all obstructions which could cause the Air Casters to loose flight and also reduces a trip hazard for the team members.

Toy 6:
Pryor to moving the chillers a forklift was attached to the leading end of the load thus giving the rigging team complete control of the moving process. No floor is absolutely level, if the slop of the floor is in the opposite direction then your intended direction of travel, a forklift is ideally suited to provide complete control of the load and extra boost when faced with a up hill slope.

Toy 7:
The outside metal platform was built to a height to coincide with the floor surface of the building’s interior. A 22 gage strip of sheet metal with it’s leading edged taped with standard carton sealing tape allowed the load module system to pass over the small gap between the platform and the building’s concrete floor.

Toy 8:
Due to the ease at which the Load Module system moves a heavy load, it is important to move at a very slow speed- ¼ to ½ walking speed is recommended; a slow speed will allow the rigging team to effectively manage any unexpected issues that may present themselves during a move.

Toy 9:
Once the chillers were inside the building they were immediately side shifted onto the special concrete foundation where they will remain throughout their useful life cycle. TFM used a Polystyrene overlay to negotiate the gap between the special foundation and the temporary interior metal deck.

Toy 10:
With the forklift reattached to the load to maintain control, and spotters at the ready, the first chiller was effortlessly moved to the far end of the special foundation.

Toy 11:
TFM’s rigging team used ASE System’s Air Jack System to remove the air caster load modules out from underneath the chillers. A convenient place under the chiller that was determined to be structurally sound was chosen as the interface point. 4 x 4 & 6x 6 blocks of wood were used to crib up to the bottom of the chiller unit. A #2J2424L air jack system with a total capacity of 64-tons and a lowered height of 7/8” is ideally suited for lifting duties of this nature.

Toy 12:
Maximum capacity of each Air Jack System is achieved at low lift height. Maximum lift height is achieved at reduced capacity which is why cribbing materials are used in conjunction with the Air Jack System when lifting extremely heavy loads. Utilizing the hand held controller a TFM team member inflated the air jack system thus lifting one end of the chiller and allowing other team members to remove the air caster load modules on that end. The air jack system was deflated and moved to the opposite end of the chiller along with the cribbing materials and the process was repeated.


Total time to move the Chillers into place: 25 minutes each.

Total time to remove the air caster system utilizing the air jack system: 8 minutes each.

At the end of the day Don Billing was beside himself with glee and joy over doing business with ASE Systems because for the first time in his long career he had rubbed shoulders with a devoted, enthusiastic and honest organization that will always have its customer’s “best interest at heart”.

 

ASE Systems
Toll Free: 800-245-2163
Fax: 281-256-7451
Cypress, TX


Copyright © 2007 Ase Systems. All rights reserved.
SEO Consulting by Seopt.com
Revised: June 4, 2007